An audit report on the Clark International Airport Corporation shows the project has been extended six times, adding 930 days to the original 365-day contract, An audit report on the Clark International Airport Corporation shows the project has been extended six times, adding 930 days to the original 365-day contract,

Auditors flag P290-M Clark air traffic control tower project delays, cost overruns

2025/12/12 09:14

MANILA, Philippines – State auditors flagged the P290.3-million New Clark Air Traffic Control Tower project, awarded in January 2021 and expected to be completed within a year, saying it remains unfinished with no target turnover date.

The 2024 audit report on the Clark International Airport Corporation (CIAC) showed the project has been extended six times, adding 930 days to the original 365-day contract, but was only 91% complete as of 2024. Costs had also risen 22% to P354.41 million.

Auditors attributed the delays to weak procurement planning, poor project monitoring and possible shortcomings in the contractor’s capacity. They also noted the project broke ground without the required building, electronic, electrical, mechanical, plumbing and sanitary permits from the Clark Development Corporation, the regulator for the Clark Freeport Zone.

Auditors stressed that building permits are mandatory under the National Building Code, with violations carrying fines of up to P20,000 or jail terms of up to two years.

“It was only on April 29, 2024 that CIAC was able to secure the necessary permits from the CDC. The absence of necessary permits during the construction period raises serious concerns regarding regulatory compliance, project authorization, and risk management,” the report read in part.

Auditors said the missing permits reflected poorly on the contractor’s ability to plan and questioned why construction continued for years without them.

“Securing permits is a fundamental requirement in the construction industry, and failure to do so casts doubt on the contractor’s capability to manage regulatory requirements effectively. This oversight not only hindered the project’s progress but also highlighted deficiencies in due diligence and adherence to standard construction protocols,” the report added.

State auditors said CIAC management failed to intervene early, allowing procedural violations to persist.

The contractor sought a suspension of the height clearance limit on March 17, 2022 – two months after the original January 2022 completion date – after the Civil Aviation Authority of the Philippines (CAAP) denied permits for the tower and tower crane for exceeding allowable height. The control tower’s proposed top elevation was 228.81 meters, compared with CAAP’s 192-meter limit, a 36.81-meter excess.

The report noted that the approval of the Final Aeronautical Study and the redesign of the 4-Instrument Flight Procedures remained pending.

With shortening the tower out of the question, CAAP required an aeronautical study for a height clearance exemption. COA said the study assessed deviations from aerodrome standards, proposed safety measures, and recommended procedures to offset the deviation.

The contractor commissioned an international firm in 2023 to conduct the three-month study, costing P3.9 million. A portion of the findings stressed that “considering the existing defenses and proposed mitigation measures, the risks associated with the new control tower in its final situation are deemed acceptable.”

The results, along with a new Height Clearance Permit application, were submitted to CAAP on October 11, 2023. As of December 31, 2024, the permit had not been issued.

“Further verification revealed that CAAP requires additional documentation to support the aeronautical study report,” the audit showed.

Auditors also found the installed elevators did not match the specified brand in the paid progress billings. While the project listed a German-made Schneider elevator, inspection revealed a different brand.

They said, “According to the approved Bill of Quantities, the contracted brand was Schneider, a German brand. However, during an inspection conducted on March 20, 2025, the installed elevator was identified as Global Fuji, a Chinese brand. A review of records confirmed that this substitution was approved by the then president and chief executive officer of CIAC.” – Rappler.com

Market Opportunity
MemeCore Logo
MemeCore Price(M)
$1.40139
$1.40139$1.40139
+3.20%
USD
MemeCore (M) Live Price Chart
Disclaimer: The articles reposted on this site are sourced from public platforms and are provided for informational purposes only. They do not necessarily reflect the views of MEXC. All rights remain with the original authors. If you believe any content infringes on third-party rights, please contact service@support.mexc.com for removal. MEXC makes no guarantees regarding the accuracy, completeness, or timeliness of the content and is not responsible for any actions taken based on the information provided. The content does not constitute financial, legal, or other professional advice, nor should it be considered a recommendation or endorsement by MEXC.

You May Also Like

Which DOGE? Musk's Cryptic Post Explodes Confusion

Which DOGE? Musk's Cryptic Post Explodes Confusion

A viral chart documenting a sharp decline in U.S. federal employment during President Trump's second term has sparked unexpected confusion in cryptocurrency markets
Share
Coinstats2025/12/20 01:13
‘One Battle After Another’ Becomes One Of This Decade’s Best-Reviewed Movies

‘One Battle After Another’ Becomes One Of This Decade’s Best-Reviewed Movies

The post ‘One Battle After Another’ Becomes One Of This Decade’s Best-Reviewed Movies appeared on BitcoinEthereumNews.com. Topline Critics have hailed Paul Thomas Anderson’s “One Battle After Another,” starring Leonardo DiCaprio, as a “masterpiece,” indicating potential Academy Awards success as it boasts near-perfect scores on review aggregators Metacritic and Rotten Tomatoes based on early reviews. Leonardo DiCaprio stars in “One Battle After Another,” which opens in theaters next week. (Photo by Jeff Spicer/Getty Images for Warner Bros. Pictures) Getty Images for Warner Bros. Pictures Key Facts “One Battle After Another” boasts a nearly perfect 97 out of a possible 100 on Metacritic based on its first 31 reviews, making it the highest-rated movie of this decade on Metacritic’s best movies of all time list. The movie also has a 96% score on Rotten Tomatoes based on the first 56 reviews, with only two reviews considered “rotten,” or negative. The Associated Press hailed the movie as “an American masterpiece,” noting the movie touches on topical political themes and depicts a society where “gun violence, white power and immigrant deportations recur in an ongoing dance, both farcical and tragic.” The movie stars DiCaprio as an ex-revolutionary who reunites with former accomplices to rescue his 16-year-old daughter when she goes missing, and Anderson has said the movie was inspired by the 1990 novel, “Vineland.” Most critics have described the movie as an action thriller with notable chase scenes, which jumps in time from DiCaprio’s character’s early days with fictional revolutionary group, the French 75, to about 15 years later, when he is pursued by foe and military leader Captain Steven Lockjaw, played by Sean Penn. The Warner Bros.-produced film was made on a big budget, estimated to be between $130 million and $175 million, and co-stars Penn, Benicio del Toro, Regina Hall and Teyana Taylor. When Will ‘one Battle After Another’ Open In Theaters And Streaming? The move opens in…
Share
BitcoinEthereumNews2025/09/18 07:35
Gold continues to hit new highs. How to invest in gold in the crypto market?

Gold continues to hit new highs. How to invest in gold in the crypto market?

As Bitcoin encounters a "value winter", real-world gold is recasting the iron curtain of value on the blockchain.
Share
PANews2025/04/14 17:12